PROJECT TIMELINE
The following is a general timeframe for the I-10 Freight Study:

Project timeline illustrating activity during the span of the I-10 Freight Study.

I-10 National Freight Study Schedule

Study begins October 2001 and ends April 2003

Corridor & Freight Demand Studies: October 2001 through August 2002
Development of Solutions & Strategies: April 2002 through January 2003
Development and Acceptance of Plans: October 2002 through April 2003

Public Involvement Activities: February 2002 through March 2003
Public Meetings: February 13 - March 7, 2002
I-10 Summit: Fall 2002